The Nana Akufo-Addo-led administration has described the $510 million contract between Ghana, Africa and Middle East Resources Investment (AMERI) Group as a “stinker.”
“It is a stinking deal,” a high profile personality at the Jubilee House whispered to Starrfmonline.com after studying the Transition Report.
The Ameri Group was contracted by the John Mahama-led administration to supply gas turbines to Ghana.
It has emerged that the young oil-producing country paid $290 million more than it should for the $220 million power generators.
An in-depth investigation into the deal by Norwegian newspaper Verdens Gang (VG) in December 2015 alleged the NDC government paid more than the actual price for the turbines on the international market.
Starrfmonline.com can confirm the economic management team of the new administration has deliberated over the deal and has the blessing of President Akufo-Addo to review the “stinking contract.”
“We can save Ghana a lot if we are able to get the right things done with this particular contract. It’s quite sad and after reviewing it, if we find out that some officials are culpable of any criminality we’ll allow the law to take its course,” the source at the presidency remarked.
“There are aspects of the deal which are not public and that also contribute to the high cost of electricity in this country. Once we are able to fix some of these things, the ordinary Ghanaian will begin to feel some reprieve.”
The former Minister of Power Dr. Kwabena Donkor is on record to have defended his government, saying there was nothing shady in the deal.
According to a December 15, 2015 edition of the Daily Guide, Dr Donkor claimed that as a build-own-operate-transfer, the NDC government “has not made any payments to Ameri and will not be making any payments for the cost of the equipment,” and that “per the agreement with Ameri, the Government of Ghana through the Volta River Authority (VRA) will only make payments to Ameri for power produced and supplied to the VRA just like any other Independent Power Producer (IPP).”
He said Ghana is required to provide “a standby Letter of Credit (LC) for an amount of $51 million, which LC has been raised.
“It must also be explained that the quoted price of $220 million in the Norwegian story for outright purchase of similar turbines is exclusive of all other costs such as auxiliaries, balance of plant, civil works, sub-station, installation of equipment, cost of financing, operation and maintenance, etc.”
Source: starrfm
Disclaimer: Opinions expressed here are those of the writers and do not reflect those of Peacefmonline.com. Peacefmonline.com accepts no responsibility legal or otherwise for their accuracy of content. Please report any inappropriate content to us, and we will evaluate it as a matter of priority. |
Please the campaign season is over. Can you hit the ground running? In one vein, you claim the deal is shaddy, in another you're saying the price quoted by the so called Norwegian story is exclusive of all other costs such as auxiliary costs, balance of plant, civil works etc. Can you please cost all these other costs before making any unsubstantiated allegations?
THEY SHOULD PREPARE FOR THIER JAIL. THAT DEVIL WHO IS CALLED KOFI ADAM, KOKU ANIKRONFOUR,AND CO
the constitution must be changed for ex-presidents to account for whatever they must have done when they were in office.
ameri is a classical definition of corruption! mahama was caught in broad daylight and he wouldn't stop steeling. it was strange especially when the whole world saw him steeling from poor Ghanaians and he kept on with this deal. its a shamme!
asem beba debi eebuboba