Work Progresses Steadily On Odaw And Korle Dredging (PHOTOS)

Engineers at Dredge Masters Ltd, the contractors for the project, are worried about the rate of continuous siltation of the channels of the Korle and Odaw Lagoons.

During a tour of lagoon to brief journalists on works undertaken, the Director of Operations of Dredge Masters, Sena Adiepena reiterated the need for residents all the sections of the channel to refrain from constantly dumping waste in the Odaw and Korle Lagoons.

The scope of works involved excavation, de-silting and refuse removal from the Odaw Channel.

These activities have included the dredging, clearing or beautification of the banks of the Odaw and Korle Lagoons.

Since the project commenced, works on the Odaw and Korle Lagoons have involved meeting timelines in time for the dangers associated with flooding experienced in that part of Accra to be mitigated, comparative to the previous year’s (2015) disaster.

Progress Of Work Done


Challenges